The full answer
Berta's migration has six stages: assess the current warehouse, design the target, convert the schema and code, move the historical data, keep it in sync with change data capture, and validate before cutting over.
1. Assess
- Inventory schemas, table sizes, growth, ETL jobs, stored procedures, reports and the users and tools that connect.
- Find the hard parts early: proprietary SQL, procedures, very large tables, and jobs that run at fixed times.
- Agree what success means: performance targets, acceptable downtime, and which reports must match exactly.
2. Design the target
- Amazon Redshift (provisioned RA3 or Serverless) as the warehouse, with S3 as the data lake for raw and historical data, often in Iceberg tables that Redshift can also query.
- Decide what moves as is, what gets redesigned, and what is retired. A migration is a good moment to drop unused tables.
3. Convert the schema and code
- AWS DMS Schema Conversion (or the AWS Schema Conversion Tool) converts tables, views and procedures to Redshift and reports what needs manual work.
- Let Redshift choose sort and distribution keys (
AUTO) at first; tune the largest tables later from real queries. - Rewrite ETL as Glue jobs, dbt models or Redshift SQL.
4. Move the historical data
- Export tables to files, preferably compressed Parquet, and transfer them to S3: AWS DataSync over the network, or AWS Direct Connect for large, steady transfers.
- Load from S3 into Redshift with
COPY, which loads files in parallel.
5. Keep it in sync
- AWS DMS with full load plus change data capture replicates ongoing changes from the source database into Redshift, so both systems stay current while users test.
6. Validate and cut over
- Compare row counts, sums and sample records per table; run the critical reports on both systems and compare results.
- Test performance with real query workloads and concurrency.
- Cut over in waves (by subject area or team), switch BI tools to Redshift, then stop replication and decommission the old system after a safe period.
Afterwards: set up monitoring, workload management, cost tracking and access control (IAM and Lake Formation), and review table design once real usage data exists.
A good answer stresses the parallel-run period with change data capture, because it is what makes a large migration low-risk: the old system stays live until the new one is proven.